Programme & Upcoming Work

Current illustrative programme

October 2021

Site mobilisation

McLaren arrive on site and begin preparation works for the start of construction.

November 2021

Crane erection

A tower crane will be delivered to site and erected over the weekend of 20th – 21st November 2021. This will require a temporary closure of this end of Commercial Road in order to allow safe delivery. Diversions will be put in place as part of this for vehicles, cyclists and pedestrians.

December 2021

Christmas site closure

The site is due to close for Christmas by 24th December 2021 and will reopen during the week commencing 3rd January 2022. The site will be secured and no work will take place between these provisional dates, which will be updated once a final decision has been taken.

During 2024

Completion

The development is currently anticipated to be completed during 2024.